1)THE FIRST STAGE
1.Scene investigation: view project overview, construction difficulty, view water and electric power supplier, roads, material handling, etc., and then implement.
2.Preparation: measurement of the base surface, design grid, sort, deepen overall façade layout.
3.Technical clarification: with the first party, supervisors, designers negotiated exterior wall construction design jointly, such as grid scheme facades, color, etc., and then turn over to the construction workers.
2)THE SECOND STAGE
1.Suspension wire: before the plastering, dropping first, then punching, after do ash cake--- by Civil construction
2.Split line: after plastering, construct the grids in strictly accordance with the design which was confirmed by proprietor and supervisor, then reserve the grid seams.
3)THE THIRD STAGE
1.Drilling positioning for anchor : to drilling 50mm hole at the bottom plate and joint of panels with percussion drill.
2.Install the anchor: fixing the anchor at the wall with expansion bolts.
3.Perimeter fastener positioning drilling: drilling around the panels with percussion drill.
4.Embedding expansion bolts
5.Strong adhesive scraping surface of energy saving fanel: Scraping the adhesives around the panels in point frame method with batch knife. Scrap the center of panel by point method, the scraping rate is more than 50%of the panel.
6.Installation of integrative panel: put the insulation and decorative panel on the professional horizontal bearing brackets.
7.Initial fixing: put the insulation and decorative panel on the professional horizontal bearing brackets.
8.Positon calibration: drilling around the panels with percussion drill.
9.Paste reinforcement: fixing the panel on the wall steadily and compact it gently. Don’t hit the surface of panels in case of surface coating damage.
10.Install the fastener: fixing the each sides of panel with mechanical fastener to ensure it safe and durable.
11.Professional glue stick to the trim strip: embed the insulation stripe into the seams of grids.
12.Sealing: caulking with self-researched waterproof sealant.
13.Clean the construction site
4)THE FORTH STAGE:COMPLETION ACCEPTANCE
1.Inspection: in strict accordance with the requirements of engineering quality.
2.Mending: mending which is not qualified, and make it perfect.
3.Inspection and acceptance: in accordance with existing national standards for construction quality acceptance.